Muskegon Heights Water Treatment Plant

Feyen Zylstra was hired to renovate the existing Muskegon Heights Water Treatment plant, as well as design the electrical systems for a major addition. Converting the existing manually operated plant to a computer-controlled, state-of-the-art facility represented over $900,000 of contract cost and was the biggest challenge. The project team upgraded the electrical distribution systems throughout the facility, installing numerous 500 KW and 800 KW emergency generators. The large addition doubles the capactity of the former water treatment plant.

For More Information, Contact:

Josh Lester  |  (616) 293-1834  |  joshual@fzcorp.com

Summary

CUSTOMER: Triangle Inc.

LOCATION: Muskegon, MI